Back to Blog

When a major pipeline operator in western North Dakota needed to locate and expose 12 miles of buried infrastructure across active well pad sites in the Bakken formation, traditional mechanical excavation posed an unacceptable risk to adjacent gas, water, and fiber optic lines. Massive Services LLC deployed a fleet of hydrovac trucks and completed the project with zero utility strikes, saving an estimated $2 million in potential damage, downtime, and regulatory penalties.

The Challenge

In late 2025, a major pipeline operator in McKenzie County, North Dakota, initiated a corridor integrity verification project spanning 12 miles of buried crude oil gathering lines. The pipeline system, originally installed between 2012 and 2016 during the height of Bakken development, ran through terrain that had since become densely populated with additional subsurface infrastructure—including high-pressure natural gas lines, municipal water mains, fiber optic communication cables, and electrical conduits.

The operator needed to physically expose the pipeline at 340 predetermined verification points to conduct visual inspections, cathodic protection assessments, and coating integrity checks. Each exposure point required excavation to depths between 4 and 9 feet, depending on the pipeline's burial depth at that location.

The complexity of this project was significant. Existing utility locate records were incomplete, with some lines installed during rapid Bakken development and never properly documented. Ground-penetrating radar surveys identified at least 47 locations where unmarked utilities crossed within 24 inches of the target pipeline. A single strike on a high-pressure gas line could result in an explosion, environmental contamination, or both—with estimated damages per incident ranging from $150,000 to $500,000 when accounting for repair costs, regulatory fines, environmental remediation, and production downtime.

Traditional mechanical excavation using backhoes or trenchers was ruled out by the operator's safety team. The density of crossing utilities, combined with the inaccuracy of existing locate records, made any contact-based digging method too risky. The operator needed a non-destructive excavation partner with the equipment, crew, and regional experience to execute this project safely and on schedule.

Our Approach

Massive Services LLC was selected for this project based on our extensive track record of pipeline daylighting work in the Bakken region and our fleet of purpose-built hydrovac equipment. Our project plan addressed three key priorities: safety, speed, and documentation accuracy.

Equipment Deployment

We mobilized four hydrovac units for this project: two Vactor HXX units with 12-yard debris tanks and 1,200-gallon water capacity, and two ring vacuum units configured for high-volume soil removal. Each truck was equipped with heated water systems capable of maintaining 140°F output temperatures—critical for the frozen ground conditions encountered during the January and February excavation windows. Supporting equipment included two water tenders for continuous supply in remote locations and a service truck for on-site maintenance.

Crew and Scheduling

We assigned a dedicated crew of 14 operators and support personnel, organized into two excavation teams working 12-hour shifts over a 6-week project timeline. Each team included a lead hydrovac operator, two nozzle operators, a vacuum truck operator, a spotter, a safety coordinator, and a site documentation specialist. This staffing model allowed us to maintain continuous operations across two excavation sites simultaneously while keeping individual crew fatigue within safe limits.

Excavation Method

At each verification point, our process followed a consistent protocol. First, our nozzle operators used pressurized water at 2,500 PSI to cut through frozen topsoil and begin liquefying the surrounding clay and shale. Water pressure was then reduced to 1,000–1,500 PSI as operators neared the expected utility depth, minimizing any risk to pipeline coatings or adjacent infrastructure. The vacuum system simultaneously removed the resulting slurry, maintaining a clean and visible excavation at all times.

When crossing utilities were encountered—which occurred at 89 of the 340 exposure points—operators switched to a low-pressure hand wand technique at 500 PSI. This allowed precise soil removal around fiber optic conduits and gas lines without applying any mechanical force to the utility surface. Each crossing utility was carefully exposed, photographed, GPS-tagged, and measured for depth and offset distance from the target pipeline.

Quality Assurance

Every excavation was documented with geo-tagged photographs, depth measurements, and condition assessments recorded in the operator's digital inspection platform. Our documentation specialist compiled daily reports that included soil conditions, utility crossing data, and any anomalies identified during exposure. This data package allowed the operator's engineering team to update their GIS records with accurate as-found utility positions—a valuable secondary outcome of the project.

The Results

340 Exposure Points Completed
0 Utility Strikes
12 mi Pipeline Corridor Verified
38 days Project Duration

The project was completed in 38 calendar days, 4 days ahead of the original 42-day schedule. All 340 verification points were excavated, inspected, and backfilled without a single utility strike, equipment incident, or safety recordable. Key outcomes included:

  • Zero utility strikes across 340 excavation points, including 89 locations with confirmed utility crossings within 24 inches of the target pipeline.
  • 23 previously undocumented utilities identified—including 8 fiber optic lines, 9 gas service laterals, and 6 water connections that were not reflected in existing locate records.
  • $2M+ in avoided damages based on the operator's internal risk model, which calculated potential costs from strikes at the 89 crossing locations using historical incident data.
  • 4 days ahead of schedule, enabled by continuous two-shift operations and efficient water resupply logistics in remote Bakken locations.
  • 14 coating defects identified during visual inspections, allowing the operator to schedule targeted repairs before any integrity failure occurred.
  • Complete GIS data update with accurate depth, position, and condition data for all exposed utilities, improving the operator's records for future maintenance activities.

Key Takeaways

This project illustrates several important principles that apply broadly to pipeline daylighting and utility exposure work in congested subsurface environments.

Hydrovac eliminates the strike risk that mechanical excavation cannot. In areas where multiple utilities share a narrow corridor—common in oilfield gathering systems—there is no safe alternative to non-destructive excavation. The cost of hydrovac is a fraction of the cost of a single utility strike when factoring in repairs, downtime, fines, and environmental remediation.

Incomplete utility records are the norm, not the exception. In this project, 23 of the 89 confirmed utility crossings (26%) were not reflected in any existing locate records. During periods of rapid infrastructure development, such as the Bakken boom of 2012–2016, documentation often lagged behind construction. Hydrovac daylighting serves as both a safety measure and a records correction tool.

Heated water systems are essential for North Dakota winter operations. Ground temperatures in McKenzie County during January and February routinely reach -10°F to -20°F at the surface. Without heated water capable of cutting through frozen soil, winter pipeline daylighting would require pre-thawing with ground heaters—a process that adds days per excavation point and dramatically increases project cost.

Crew experience in the Bakken matters. Our operators' familiarity with Bakken soil conditions—including the region's characteristic layering of clay, shale, and gravel deposits—allowed for efficient pressure adjustments at each excavation point. Experienced crews can read soil behavior in real time, adjusting water pressure and vacuum power to maintain both safety and productivity.

For pipeline operators, utility companies, and general contractors working in the Bakken region, this case study demonstrates why hydrovac excavation has become the standard of care for any project involving subsurface utility exposure. The technology, combined with experienced crews and proper planning, delivers results that mechanical excavation simply cannot match in congested utility environments.

Need Pipeline Daylighting or Utility Exposure Services?

Massive Services LLC operates across North Dakota and Colorado with a fleet of hydrovac trucks ready to mobilize. Contact us to discuss your next project.